Golder Uses PLAXIS 3D in Tunneling Construction Project

Located on Hong Kong Island, the Western Island Line is a fully underground railway that alleviates heavy traffic congestion in the western district. A USD 200 million Western Island Line contract involved constructing two single-track tunnels surrounded by existing infrastructure. Golder Associates (Hong Kong) Limited (GAHK) was consulted to help the contractors overcome the project’s unprecedented geotechnical challenges. GAHK needed to meet the required special grouting protective measures beneath several buildings along the tunneling route.

IMG_8455

The Tunnel Dismantling Machine (TDM)  was the first of its kind in the world and won the "Product or Equipment Innovation of the
Year” award in New Civil Engineer’s International Tunneling Awards 2013.

GAHK provided geotechnical services for tunneling, dismantling, and excavating. The team implemented 3D finite element analysis, which was less common back in 2009 during the construction of the project. The 3D finite element modeling enabled the team to overcome limitations while considering the large number of individual piles and unique alignment of the tunnels. The team analyzed and modeled previously difficult or impossible situations, developing a real and rigorous 3D analysis of the soil-structure interaction.

IMG_2372

Golder had to consider that the alignment of the tunnels is at a skew angle to the orientation of the existing buildings.

Parametric modeling and analysis helped optimize design, saving time and costs while enhancing tunneling safety. Geotechnical engineering applications supported a solution that optimized the amount of required grouting protection works for the buildings and saved construction time by up to three months. This practice also saved 7,000 cubic meters of grout and concrete material, as well as 1,500 tons of carbon dioxide emissions. The 3D analysis helped avoid temporarily rerouting traffic to install grouting tubes in a highly congested area, saving up to 200,000 tons of carbon dioxide emissions. The more rigorous 3D analysis shows savings in less overdesign while still meeting all serviceability and factor of safety requirements. Now, 10 years later, GAHK plans to build upon the project’s previous success by creating a digital twin for future tunneling projects from planning through construction to maintenance stage.

002

PLAXIS 3D was used to design for the shotcrete thickness and strength required for the incremental dismantling process involving time.

PLAXIS enabled the team to model and analyze the contractor’s design scheme during tendering, to design associated underground structures, and to perform construction simulation. MicroStation facilitated the production of construction drawings from 3D models. The project won numerous awards for technical excellence, which would not have been possible without PLAXIS geotechnical analysis for the project’s tunneling, dismantling, and excavating works.

001

3D analysis helped predict the pile lateral displacement and settlement, as well as pile bending moment, axial force, and shear force.


Discover the PLAXIS Productivity Strategies series featuring blogs, LinkedIn Live sessions, and webinars.

Learn the top efficiency tips to solve your common problems.

Discover PLAXIS Productivity Strategies


 

Webinar Series

Watch the Virtuosity team design a brand-new building from Concept to Construction! 

Join us on our Digital Construction journey in a webinar series where we take you step-by-step through the conceptual and preliminary building design processes. We will be using a variety of different software products from our collection! 

To learn more about what you can accomplish with Virtuosity, you can register for the entire webinar series below or choose to just join in session 5 which is dedicated specifically to Structural Analysis!

Register Now

The tools that you will see showcased in this nine-part webinar series are: 

Bentley Workflow